Kolkata, September 1
Coal India Limited (CIL) supplies to power sector at 243.3 million tonnes (MTs) achieved 108 per cent of annual action plan (AAP) target of 225.4 MTs, progressive till August of the financial year 2022-23 (FY’23).
Supplies overshot the target by nearly 18 MTs. The company also breached its AAP target of 276 MTs for total off-take achieving 102.5 per cent satisfaction. Total supplies have risen sharply to 283 MTs, during the period under reference with a jump of 7 MTs over the target.
CIL’s supplies of 243.3 MTs to power sector during April-August’22 were 38.1 MTs more compared to same period last year posting a double digit growth of 18.6 per cent. Supplies were 205.2 MTs for the same period last year.
At 283 MTs total coal off-take of the company, progressive till August’22 of current fiscal, increased by 23.6 MTs in volume terms against 259.4 MTs of last year. The growth is 9.1 per cent. Diminishing fears of coal shortage, coal stock at power plants is close to 30 MTs, including imported coal, ending August 22 (till 29th). This is substantially higher than 12.8 MTs of August ’21 when the stock plummeted by 11.2 MTs in a month.
Improved supplies from CIL helped the stock stabilizing at power plants. Closing stock for the month of August’22 is a six year high barring 2020 when pandemic fuelled slowdown saw the stock at 37.7 MTs.
Producing 253.3 MTs of coal during April-August’22 CIL logged a double-digit year-on-year growth of 21 per cent. This is a strong 44.1 MT increase in absolute terms against 209.2 MTs of last year’s same period.
This level of increase was achieved despite increased downpour across all the areas of WCL and MCL. WCL on an average received 54 per cent more rainfall since 1st June till August end during the ongoing fiscal, for a similar period of last year, while the rainfall was 57 per cent more in the areas of MCL.
Amidst this, CIL’s production for August’22 posted 8.5 per cent growth at 46.2 MTs. This is a jump of 3.6 MTs compared to 42.6 MTs of August’21. Total coal off-take of 51.1 MTs for the month of August ’22 has also surpassed the AAP target of 47.5 MTs which is an achievement of 108 per cent. Compared to 48.6 MTs of August’21 the growth is 5 per cent.
In August’22 CIL supplied 43.8 MTs of coal to thermal power plants posting 16 per cent growth against last year’s 37.8 MTs.
With a coal stock of 31 MTs at CIL’s pitheads, around 30 MTs stock at power plants, and a little over 10 MTs at CIL’s sidings, goods sheds, private washeries, ports, captive plants there is sufficient availability of coal in the system