Ahmedabad, December 19
NTPC Limited on Thursday announced the commissioning second part capacity of 30 MW out of 150 MW Gujarat Solar PV Project of NTPC Renewable Energy Limited (NTPC REL).
The power major declared December 11, 2024 as the commercial operation date (COD) of second part capacity of the project.
“We wish to inform you that on the basis of certificate dated 18.12.2024 issued by Gujarat Energy Development Agency, second part capacity of 30 MW out of 150 MW Gujarat Solar PV Project in Mesanka, Gujarat of NTPC Renewable Energy Limited (NTPC REL), a stepdown subsidiary of NTPC Limited through its subsidiary NTPC Green Energy Limited, is declared on Commercial Operation w.e.f. 00:00 Hrs of 11.12.2024,” NTPC Limited said in a regulatory filing today.
The first part capacity of 60 MW has already been declared on commercial operation with effect from July 29, 2024.
With this, the total installed and commercial capacity of NTPC group has now become 76560.68 MW.