New Delhi, June 2
Power major NTPC Limited has fully commissioned the 300 Mw Mokhra Solar PV Project after making its fifth part capacity of 50 MW commercially operational in Bikanar of Rajasthan.
“Consequent upon successful commissioning, fifth and last part capacity of 50 MW of 300 MW Nokhra Solar PV Project of NTPC Green Energy Limited (A wholly owned Subsidiary of NTPC Limited) at Bikaner, Rajasthan, is declared on Commercial Operation w.e.f. 00:00 Hrs. of 03.06.2023,” NTPC Limited said in a regulatory filing.
The first part capacity of 100 MW was declared on commercial operation w.e.f. 20.12.2022, second part capacity of 50 MW w.e.f. 30.12.2022, third part capacity of 50 MW w.e.f. 16.02.2023 and fourth part capacity of 50 MW w.e.f. 01.04.2023, the company said.
With this, installed and commercial capacity of NTPC Green Energy Limited will become 2711 MW while group installed and commercial capacity of NTPC will become 72354 MW.